# Architecture: Evaluation Triggers
|
|
|
|
The [Scheduling in Nomad][] internals documentation covers the path that an
|
|
evaluation takes through the leader, worker, and plan applier. This document
|
|
describes what events within the cluster cause Evaluations to be created.
|
|
|
|
Evaluations have a `TriggeredBy` field which is always one of the values defined
|
|
in [`structs.go`][]:
|
|
|
|
```
|
|
const (
|
|
EvalTriggerJobRegister = "job-register"
|
|
EvalTriggerJobDeregister = "job-deregister"
|
|
EvalTriggerPeriodicJob = "periodic-job"
|
|
EvalTriggerNodeDrain = "node-drain"
|
|
EvalTriggerNodeUpdate = "node-update"
|
|
EvalTriggerAllocStop = "alloc-stop"
|
|
EvalTriggerScheduled = "scheduled"
|
|
EvalTriggerRollingUpdate = "rolling-update"
|
|
EvalTriggerDeploymentWatcher = "deployment-watcher"
|
|
EvalTriggerFailedFollowUp = "failed-follow-up"
|
|
EvalTriggerMaxPlans = "max-plan-attempts"
|
|
EvalTriggerRetryFailedAlloc = "alloc-failure"
|
|
EvalTriggerQueuedAllocs = "queued-allocs"
|
|
EvalTriggerPreemption = "preemption"
|
|
EvalTriggerScaling = "job-scaling"
|
|
EvalTriggerMaxDisconnectTimeout = "max-disconnect-timeout"
|
|
EvalTriggerReconnect = "reconnect"
|
|
)
|
|
```
|
|
|
|
The list below covers each trigger and what can trigger it.
|
|
|
|
* **job-register**: Creating or updating a Job will result in 1 Evaluation
|
|
created, plus any follow-up Evaluations associated with scheduling, planning,
|
|
or deployments.
|
|
* **job-deregister**: Stopping a Job will result in 1 Evaluation created, plus
|
|
any follow-up Evaluations associated with scheduling, planning, or
|
|
deployments.
|
|
* **periodic-job**: A periodic job that hits its timer and dispatches a child
|
|
job will result in 1 Evaluation created, plus any additional Evaluations
|
|
associated with scheduling or planning.
|
|
* **node-drain**: Draining a node will create 1 Evaluation for each Job on the
|
|
node that's draining, plus any additional Evaluations associated with
|
|
scheduling or planning.
|
|
* **node-update**: When the fingerprint of a client node has changed or the node
|
|
has changed state (from up to down), Nomad creates 1 Evaluation for each Job
|
|
running on the Node, plus 1 Evaluation for each system job that has
|
|
`datacenters` that include the datacenter for that Node.
|
|
* **alloc-stop**: When the API that serves the `nomad alloc stop` command is
|
|
hit, Nomad creates 1 Evaluation.
|
|
* **scheduled**: Nomad's internal housekeeping will periodically create
|
|
Evaluations for garbage collection.
|
|
* **rolling-update**: When a `system` job is updated, the [`update`][] block's
|
|
`stagger` field controls how many Allocations will be scheduled at a time. The
|
|
scheduler will create 1 Evaluation to follow-up for the next set.
|
|
* **deployment-watcher**: When a `service` job is updated, the [`update`][]
|
|
block controls how many Allocations will be scheduled at a time. The
|
|
deployment watcher runs on the leader and monitors Allocation healthy. It will
|
|
create 1 Evaluation when the Deployment has reached the next step.
|
|
* **failed-follow-up**: Evaluations that hit a delivery limit and will not be
|
|
retried by the eval broker are marked as failed. The leader periodically
|
|
reaps failed Evaluations and creates 1 new Evaluation for these, with a delay.
|
|
* **max-plan-attempts**: The scheduler will retry Evaluations that are rejected
|
|
by the plan applier with a new cluster state snapshot. If the scheduler
|
|
exceeds the maximum number of retries, it will create 1 new Evaluation in the
|
|
`blocked` state.
|
|
* **alloc-failure**: If an Allocation fails and exceeds its maximum
|
|
[`restart` attempts][], Nomad creates 1 new Evaluation.
|
|
* **queued-allocs**: When a scheduler processes an Evaluation, it may not be
|
|
able to place all Allocations. It will create 1 new Evaluation in the
|
|
`blocked` state to be processed later when node updates arrive.
|
|
* **preemption**: When Allocations are preempted, the plan applier creates 1
|
|
Evaluation for each Job that has been preempted.
|
|
* **job-scaling**: Scaling a Job will result in 1 Evaluation created, plus any
|
|
follow-up Evaluations associated with scheduling, planning, or deployments.
|
|
* **max-disconnect-timeout**: When an Allocation is in the `unknown` state for
|
|
longer than the [`max_client_disconnect`][] window, the scheduler will create
|
|
1 Evaluation.
|
|
* **reconnect**: When a Node in the `disconnected` state reconnects, Nomad will
|
|
create 1 Evaluation per job with an allocation on the reconnected Node.
|
|
|
|
## Follow-up Evaluations
|
|
|
|
Almost any Evaluation processed by the scheduler can result in additional
|
|
Evaluations being created, whether because the scheduler needs to follow-up from
|
|
failed scheduling or because the resulting plan changes the state of the
|
|
cluster. This can result in a large number of Evaluations when the cluster is in
|
|
an unstable state with frequent changes.
|
|
|
|
Consider the following example where a node running 1 system job and 2 service
|
|
jobs misses its heartbeat and is marked lost. The Evaluation for the system job
|
|
is successfully planned. One of the service jobs no longer meets constraints. The
|
|
other service job is successfully scheduled but the resulting plan is rejected
|
|
because the scheduler has fallen behind in raft replication. A total of 6
|
|
Evaluations are created.
|
|
|
|
```mermaid
|
|
flowchart TD
|
|
|
|
event((Node\nmisses\nheartbeat))
|
|
|
|
system([system\nnode-update])
|
|
service1([service 1\nnode-update])
|
|
service2([service 2\nnode-update])
|
|
|
|
blocked([service 1\nblocked\nqueued-allocs])
|
|
failed([service 2\nfailed\nmax-plan-attempts])
|
|
followup([service 2\nfailed-follow-up])
|
|
|
|
%% style classes
|
|
classDef eval fill:#d5f6ea,stroke-width:4px,stroke:#1d9467
|
|
classDef other fill:#d5f6ea,stroke:#1d9467
|
|
class event other;
|
|
class system,service1,service2,blocked,failed,followup eval;
|
|
|
|
event --> system
|
|
event --> service1
|
|
event --> service2
|
|
|
|
service1 --> blocked
|
|
|
|
service2 --> failed
|
|
failed --> followup
|
|
```
|
|
|
|
Next, consider this example where a `service` job has been updated. The task
|
|
group has `count = 3` and the following `update` block:
|
|
|
|
```hcl
|
|
update {
|
|
max_parallel = 1
|
|
canary = 1
|
|
}
|
|
```
|
|
|
|
After each Evaluation is processed, the Deployment Watcher will be waiting to
|
|
receive information on updated Allocation health. Then it will emit a new
|
|
Evaluation for the next step. A total of 4 Evaluations are created.
|
|
|
|
```mermaid
|
|
flowchart TD
|
|
|
|
registerEvent((Job\nRegister))
|
|
alloc1health((Canary\nHealthy))
|
|
alloc2health((Alloc 2\nHealthy))
|
|
alloc3health((Alloc 3\nHealthy))
|
|
|
|
register([job-register])
|
|
dwPostCanary([deployment-watcher])
|
|
dwPostAlloc2([deployment-watcher])
|
|
dwPostAlloc3([deployment-watcher])
|
|
|
|
%% style classes
|
|
classDef eval fill:#d5f6ea,stroke-width:4px,stroke:#1d9467
|
|
classDef other fill:#d5f6ea,stroke:#1d9467
|
|
class registerEvent,alloc1health,alloc2health,alloc3health other
|
|
class register,dwPostCanary,dwPostAlloc2,dwPostAlloc3 eval
|
|
|
|
registerEvent --> register
|
|
register --> wait1
|
|
alloc1health --> wait1
|
|
wait1 --> dwPostCanary
|
|
|
|
dwPostCanary --> wait2
|
|
alloc2health --> wait2
|
|
wait2 --> dwPostAlloc2
|
|
|
|
dwPostAlloc2 --> wait3
|
|
alloc3health --> wait3
|
|
wait3 --> dwPostAlloc3
|
|
|
|
```
|
|
|
|
Lastly, consider this example where 2 nodes each running 5 Allocations that are
|
|
all for system jobs are "flapping" by missing heartbeats and then
|
|
re-registering, or frequently changing fingerprints. This diagram will show the
|
|
results from each node going down once and then coming back up.
|
|
|
|
```mermaid
|
|
flowchart TD
|
|
|
|
%% style classes
|
|
classDef eval fill:#d5f6ea,stroke-width:4px,stroke:#1d9467
|
|
classDef other fill:#d5f6ea,stroke:#1d9467
|
|
|
|
eventAdown((Node A\nmisses\nheartbeat))
|
|
eventAup((Node A\nheartbeats))
|
|
eventBdown((Node B\nmisses\nheartbeat))
|
|
eventBup((Node B\nheartbeats))
|
|
|
|
eventAdown --> eventAup
|
|
eventBdown --> eventBup
|
|
|
|
A01down([job 1 node A\nnode-update])
|
|
A02down([job 2 node A\nnode-update])
|
|
A03down([job 3 node A\nnode-update])
|
|
A04down([job 4 node A\nnode-update])
|
|
A05down([job 5 node A\nnode-update])
|
|
|
|
B01down([job 1 node B\nnode-update])
|
|
B02down([job 2 node B\nnode-update])
|
|
B03down([job 3 node B\nnode-update])
|
|
B04down([job 4 node B\nnode-update])
|
|
B05down([job 5 node B\nnode-update])
|
|
|
|
A01up([job 1 node A\nnode-update])
|
|
A02up([job 2 node A\nnode-update])
|
|
A03up([job 3 node A\nnode-update])
|
|
A04up([job 4 node A\nnode-update])
|
|
A05up([job 5 node A\nnode-update])
|
|
|
|
B01up([job 1 node B\nnode-update])
|
|
B02up([job 2 node B\nnode-update])
|
|
B03up([job 3 node B\nnode-update])
|
|
B04up([job 4 node B\nnode-update])
|
|
B05up([job 5 node B\nnode-update])
|
|
|
|
eventAdown:::other --> A01down:::eval
|
|
eventAdown:::other --> A02down:::eval
|
|
eventAdown:::other --> A03down:::eval
|
|
eventAdown:::other --> A04down:::eval
|
|
eventAdown:::other --> A05down:::eval
|
|
|
|
eventAup:::other --> A01up:::eval
|
|
eventAup:::other --> A02up:::eval
|
|
eventAup:::other --> A03up:::eval
|
|
eventAup:::other --> A04up:::eval
|
|
eventAup:::other --> A05up:::eval
|
|
|
|
eventBdown:::other --> B01down:::eval
|
|
eventBdown:::other --> B02down:::eval
|
|
eventBdown:::other --> B03down:::eval
|
|
eventBdown:::other --> B04down:::eval
|
|
eventBdown:::other --> B05down:::eval
|
|
|
|
eventBup:::other --> B01up:::eval
|
|
eventBup:::other --> B02up:::eval
|
|
eventBup:::other --> B03up:::eval
|
|
eventBup:::other --> B04up:::eval
|
|
eventBup:::other --> B05up:::eval
|
|
|
|
```
|
|
|
|
You can extrapolate this example to large clusters: 100 nodes each running 10
|
|
system jobs and 40 service jobs that go down once and come back up will result
|
|
in 100 * 40 * 2 == 8000 Evaluations created for the service jobs, which will
|
|
result in rescheduling of service allocations to new nodes. For the system jobs,
|
|
2000 Evaluations will be created and all of these will be no-op Evaluations that
|
|
will still need to be replicated to all raft peers, canceled by the scheduler,
|
|
and eventually need to be garbage collected.
|
|
|
|
|
|
|
|
[Scheduling in Nomad]: https://www.nomadproject.io/docs/internals/scheduling/scheduling
|
|
[`structs.go`]: https://github.com/hashicorp/nomad/blob/v1.4.0-beta.1/nomad/structs/structs.go#L10857-L10875
|
|
[`update`]: https://www.nomadproject.io/docs/job-specification/update
|
|
[`restart` attempts]: https://www.nomadproject.io/docs/job-specification/restart
|
|
[`max_client_disconnect`]: https://www.nomadproject.io/docs/job-specification/group#max-client-disconnect
|